top of page

Street Haven Construction Notice Board

Street Haven 60th Anniversary Logo_edited.png

Posted on

Wednesday, July 16, 2025

Renovation Works Notice

607 St Clair Avenue W

Start Date:

July 16, 2025

End Date:

July 22, 2025

Notice of Meeting Room Remodelling Completion


We are pleased to inform you that the renovation works for the meeting room are scheduled to be completed by Friday, July 18, 2025.


We appreciate your cooperation and patience throughout the duration of this project. Please feel free to reach out with any questions or if further assistance is required.

For questions, email:

Recent Project Updates

Filter by Location

July 16, 2025 at 7:16:03 p.m.

Posted on

607 St Clair Avenue W

Renovation Works Notice

Start Date:

End Date:

July 16, 2025

July 22, 2025

Notice of Meeting Room Remodelling Completion


We are pleased to inform you that the renovation works for the meeting room are scheduled to be completed…

July 16, 2025 at 6:48:34 p.m.

Posted on

87 Pembroke St

Renovation Works Notice

Start Date:

End Date:

July 18, 2025

August 1, 2025

Notice of Exterior Footing Work for New Fire Escape


Please be advised that exterior footing work for the installation of a new fire escape will…

July 7, 2025 at 3:25:10 p.m.

Posted on

87 Pembroke St

Renovation Work Notice

Start Date:

End Date:

July 8, 2025

July 18, 2025

Structural framing work will commence at Attic Renovation on Tuesday, July 8, 2025. This phase will include the erection of structural components such as walls.

Sonderbloom is supporting Street Haven's renovation as development managers. Learn more about Sonderbloom, our team and our other projects.

bottom of page